The Hon’ble National Company Law Tribunal (NCLT), New Delhi Bench, Court-IV, vide its Order dated 25th February 2025, under Company Petition no. (IB)- 558(ND)/2024, in the matter of M/s IL&FS Financial Services Limited vs. M/s. Ansal Properties and Infrastructure Limited has approved the initiation of Corporate Insolvency Resolution Process (CIRP) against “Ansal Properties and Infrastructure Limited and appointed Mr. Navneet Kumar Gupta as IRP having Registration No. IBBI/IPA-001/IP-P00001/2016-2017/10009.

(CIRP process Email id: cirpofapil@minervaresolutions.com)

Click here to view the CIRP website

Partner With Us
Customer Query
  • New Customer   Existing Customer
  • Home
  • Construction Update

Olympus Lake View - Scaffolding for external plaster started.

Media Enclave Tower-C2, Raft foundation casting work in progress.

Jeevan enclave - Pooja Ceremony before starting of excavation work at Jeevan Enclave Tower-A &B1.

Shopping Square Sec A Approx 12900 Sq ft Stich Slab Totality Completed