Olympus Lake View - Scaffolding for external plaster started.
Media Enclave Tower-C2, Raft foundation casting work in progress.
Jeevan enclave - Pooja Ceremony before starting of excavation work at Jeevan Enclave Tower-A &B1.
Bliss Delight - 4 Pilling Rigs On Site
Railway Over Bridge (ROB) Construction in Full Swing
Sector-J-Media Enclave Tower-B3, Terrace slab Casting work in progress.
Sec J2- Palm Floor Block 9-10,Ground Floor roof Slab Casting work in progress .
Jeevan Enclave Tower-C2 slab work in progress
Shopping Square Sec A Approx 12900 Sq ft Stich Slab Totality Completed
Palm Floor-(Sec-J2) Block-247-248 Second Floor Roof Slab Casting Work in Progress
Palm floors-(Sec-J2) Block-223-224 Ground Floor Roof Slab Casting Work in Progress